Crossdykes Wind Farm 110m met-tower
Posted on 9th August 2021 at 19:47
RADTech/CarlC completed installation and commissioned Crossdykes WF 110m meteorological tower in April 2021. Despite COVID restrictions the project was completed with great success. The met-tower project included the tower manufacturing, installation, instrumentation, data logger system, GSM/GPRS access as well as SCADA integration via Modbus protocol and fibre optic connectivity.
The tower is further modified to accommodate area wide high-speed Internet connectivity via multiple Wi-Fi nodes. The Wi-Fi system was provided by Briskona Internet Service Provider, Sterling, UK.
Tagged as: Briskona, CarlC A/S, Crossdykes Wind Farm, Met-Masts, Meteorlogical Towers, Muirhall Energy